Case study: a Tilburg DC saved 11% by splitting the award
A 3PL re-racking a Tilburg distribution centre ran a four-line RFQ to six suppliers. Splitting the award across two specialists beat the best single bundled bid by 11% — with a shorter lead time.
By LayTech
A third-party logistics operator needed to re-rack a distribution centre in Tilburg: adjustable pallet racking, a steel mezzanine, dock levellers and a small order-picker fleet. They ran it as a four-line RFQ to six verified suppliers.
The bundled bids looked close
On a whole-project basis, the three lowest bundled quotes were within 4% of each other. On price alone, the buyer would have picked one integrator and moved on.
Line by line told a different story
Broken out per line, the picture changed:
- Supplier A was sharpest on racking but mid-pack on the mezzanine.
- Supplier C was strongest on the mezzanine and dock equipment.
- No single supplier led on more than two lines.
The split-award result
Awarding racking to A and the mezzanine + dock lines to C — each scored on price, lead time and warranty — came in 11% below the best single bundled bid, and the combined lead time was two weeks shorter because both specialists built in parallel.
The procurement file was fully auditable: four lines, six suppliers, one MEAT rubric, two awards each with a documented reason. That is the difference between buying a fit-out and procuring one.